Prepare a pre-feasibility study for a Green Corridor to improve safe pedestrian access to public transport in Keur Massar and strengthen institutional capacities for climate-resilient, inclusive street design and participatory project development in Dakar.
WP1 Baseline study
- Review existing data and studies; identify gaps; conduct additional data collection (e.g. traffic counts, user surveys, air quality and environmental measurements).
- Analyse urban context and land use; travel demand (quantitative and qualitative); supply quality and capacity for all modes; safety and conflicts; environmental quality; climate stress (heat, flooding); gender and social inclusion; institutional and legal framework; state-of-the-art references (incl. regional examples).
- Deliverables: D1.1 Methodological orientation (inception) report; D1.2 Baseline report; D1.3 Slide deck; D1.4 Provision of raw, machine-readable and editable data and media.
WP2 Participation process
- Map stakeholders (incl. vulnerable groups, women, persons with disabilities, street vendors, informal transport, neighbourhood groups, local and national authorities).
- Design and implement an inclusive, gender-responsive participation strategy (incl. at least one virtual measure); facilitate workshops, mediation as needed; document and evaluate results.
- Deliverables: D2.1 Stakeholder analysis (report); D2.2 Slides; D2.3 Participation Strategy; D2.4 Facilitation materials/templates (editable); D2.5 Results report with inputs for corridor requirements; D2.6 Reference Toolkit for participatory processes (FR/EN) to enable replication.
WP3 Pre-feasibility Study (PFS) Green Corridor
- Identify and appraise design/traffic management alternatives; SWOT; recommend preferred alternative in consultation with CETUD and local administrations.
- Produce ?15 preliminary and 10 final conceptual designs (street sections/intersections, allocation of road space, speeds, traffic regulation, green infrastructure, lighting/shading, materials, signage; capacity for all modes).
- Conduct preliminary Environmental and Social Impact Assessment and cultural/heritage screening; Cost-Benefit Analysis incl. climate benefits; risk assessment (strategic/project risks); outline financing options and sources.
- Prepare implementation strategy (phasing, data/engineering needs, roles/responsibilities, maintenance concept, financing structure), communication strategy (public and stakeholder messaging, best practice), investor pitch deck.
- Prepare an Action Plan on Secure Bus Stops aligned with metropolitan frameworks (topic may be adjusted).
- Deliverables: D3.1 Alternatives & conceptual designs; D3.2 Preliminary Impact Assessment; D3.3 CBA; D3.4 Risk Assessment; D3.5 PFS; D3.6 Pitch deck; D3.7 Implementation Strategy; D3.8 Communication Strategy; D3.9 Action Plan.
WP4 Training conceptualisation and implementation
- Design and deliver a 120-hour training (?3 seminars x 3 days + self-learning) on: sustainable mobility and street design, public space management and climate resilience, project development from concept to operation; integrate co-creative work on Green Corridor elements.
- Train-the-trainer: coach 5 staff (CETUD/local authorities) to replicate training; refine materials after pilot.
- Develop replicable materials: presentations, scripts, videos (?240 min), templates (surveys, fieldwork), instructor"s manual, implementation plan and guidance (checklists, certificate templates), evaluation tools; final training report with lessons learned.
- Deliverables: D4.1 Training concept; D4.2 Training materials; D4.3 Instructor"s manual; D4.4 Implementation plan & guidance; D4.5 Training report.
Governance and cooperation
- Work in close coordination with CETUD, MiTTA and a Technical Committee established by CETUD; align with the RTC project context and ongoing bus station redevelopment.
- Provide brief monthly status reports (2 pages) in French (activities, outputs in progress, impacts, decisions needed, expert days).
- Contribute to knowledge sharing (events, publications) and support evaluation of knowledge management effectiveness.
Reporting and languages
- Main deliverables in French; the participation toolkit in FR/EN; raw data and media in editable, machine-readable formats as specified.
Indicative duration and milestones (from contract start)
- WP1: D1.1 at 1 month; D1.2-1.4 at 3 months.
- WP2: D2.1-2.2 at 2 months; D2.3 at 4 months; D2.4 at 6 months; D2.5 at 10 months; D2.6 at 11 months.
- WP3: Designs drafts at 3/8 months, final at 12 months; Impact/CBA/Risk drafts 6-10 months, finals at 12 months; PFS draft 9 months, final 12 months; Pitch/Implementation/Communication drafts 10 months, finals 12 months; Action Plan draft 10 months, final 12 months.
- WP4: Concept draft/final 4/6 months; Materials 6/7 months; Instructor"s manual 6/8 months; Implementation plan 8/9 months; Training report 12 months.